Project: Construction of the dividing Dam of Bodorna reservoir and reserve channel
Location: Georgia, Dusheti Municipality
Client: Georgian Water and Power LTD (GWP)
Timeline: 07.06.2019- 07.07.2019
Main quantities:
• Soil excavation 19530 m3;
• sand-gravel layer 8350m2;
• Basalt Reinforcement 10700 m2;
• Concrete works 1620 m3;